Raw Materials Risk

Carmakers face a decade of costlier copper and nickel

Published Modified
4 min
Exploded 3D view of an electric vehicle with separated body panels, battery pack and drivetrain components.
Every motor, harness and battery pack starts as metal

Recent research predicts copper and nickel prices to roughly double by 2035 as trade curbs multiply and supply lags demand. For vehicle plants built on metal, a trade deal may not rescue material cost.

At a glance

Coface expects copper and nickel prices to roughly double over the next decade as supply growth trails demand across key industrial metals.

Supply is forecast to grow 0.4% a year for aluminium, 1.0% for copper and 1.5% for nickel, against demand growth of 1.8%.

Import and export restrictions reached 1,138 by the end of 2025, up from 357 a decade earlier, while China dominates refining.

Coface economist Marcos Carias advises North American manufacturers to plan for higher metal costs rather than wait for a trade deal.

Copper and nickel prices could roughly double over the next decade, according to a new report from trade credit insurer, Coface. But for carmakers and Tier 1 suppliers, this is in fact less a commodity story, than a cost-engineering one. Every motor winding, wiring harness, battery cathode and aluminium casting in a vehicle plant’s bill of materials sits downstream of the same tightening market.

The report, Back to the Future (Cycle), draws on production, consumption and price data from the London Metal Exchange, the US Geological Survey, the World Bank and the International Energy Agency. Its central finding? Supply is falling behind demand, and the gap looks far more structural than seasonal.

Growth that cannot keep pace

Coface expects supply to grow by just 0.4% a year for aluminium, 1.0% for copper and 1.5% for nickel. Demand, by contrast, is projected to rise by 1.8% a year. Those fractions look modest, but compounded over a decade they open a shortfall that coverage of the report puts at around 10% of demand for the three metals by 2035. Plant buyers do not purchase at the average, they purchase at the margin, and the margin is where prices move first.

Metallic foundations of vehicle plants

Nickel is the cell maker’s concern first, since it sits in high-energy cathodes, but the cost travels to pack assemblers and then to the vehicle line. Copper runs through traction motors, inverters, busbars and the harnesses that tie together increasingly electrified architectures. Aluminium appears in body structures, large castings and battery enclosures, while steel remains the backbone of the body-in-white. A price shock in any one of them lands on a different line item, which makes it harder to absorb through a single procurement lever.

Restrictions on the rise

Trade policy is, to say the least, adding friction to the carmaking ecosystem. By the end of 2025, 1,138 import and export restrictions on critical minerals were in force - up from 357 a decade earlier. This is more than a threefold increase. Each measure may be defensible on its own terms - yet together they make the physical movement of metal slower, costlier and harder to forecast, which is the opposite of what a just-in-time assembly plant needs.

Supply is struggling to keep pace with demand

Aluminium, refined copper and refined nickel, observed and projected, million tonnes (Mt), 2001 to 2040. Select a metal to open its chart.

Aluminium2035 gap to Net Zero demand: 14.3 Mt (14%)
Observed consumptionBaseline scenario (demand)Net Zero scenario (demand)Announced supply projects
Projections050100150200120052010201520202025203020352040Mt2001Observed consumption: 23.6 Mt2002Observed consumption: 25.5 Mt2003Observed consumption: 27.6 Mt2004Observed consumption: 30.0 Mt2005Observed consumption: 31.6 Mt2006Observed consumption: 33.9 Mt2007Observed consumption: 37.4 Mt2008Observed consumption: 37.0 Mt2009Observed consumption: 34.8 Mt2010Observed consumption: 40.4 Mt2011Observed consumption: 44.9 Mt2012Observed consumption: 49.3 Mt2013Observed consumption: 46.5 Mt2014Observed consumption: 54.0 Mt2015Observed consumption: 57.4 Mt2016Observed consumption: 59.0 Mt2017Observed consumption: 63.2 Mt2018Observed consumption: 66.0 Mt2019Observed consumption: 63.2 Mt2020Observed consumption: 64.8 Mt2021Observed consumption: 68.5 Mt2022Observed consumption: 68.1 Mt2023Observed consumption: 69.3 Mt2024Observed consumption: 72.0 MtBaseline scenario: 72.0 MtNet Zero scenario: 72.0 MtAnnounced supply projects: 72.8 Mt2025 (projection)Baseline scenario: 73.7 MtNet Zero scenario: 74.4 MtAnnounced supply projects: 74.1 Mt2026 (projection)Baseline scenario: 75.5 MtNet Zero scenario: 76.8 MtAnnounced supply projects: 75.4 Mt2027 (projection)Baseline scenario: 77.3 MtNet Zero scenario: 79.4 MtAnnounced supply projects: 76.8 Mt2028 (projection)Baseline scenario: 79.2 MtNet Zero scenario: 82.0 MtAnnounced supply projects: 78.2 Mt2029 (projection)Baseline scenario: 81.1 MtNet Zero scenario: 84.7 MtAnnounced supply projects: 79.6 Mt2030 (projection)Baseline scenario: 83.1 MtNet Zero scenario: 87.5 MtAnnounced supply projects: 81.1 Mt2031 (projection)Baseline scenario: 85.1 MtNet Zero scenario: 90.5 MtAnnounced supply projects: 82.6 Mt2032 (projection)Baseline scenario: 87.2 MtNet Zero scenario: 93.5 MtAnnounced supply projects: 84.1 Mt2033 (projection)Baseline scenario: 89.3 MtNet Zero scenario: 96.6 MtAnnounced supply projects: 85.6 Mt2034 (projection)Baseline scenario: 91.5 MtNet Zero scenario: 99.8 MtAnnounced supply projects: 87.2 Mt2035 (projection)Baseline scenario: 93.7 MtNet Zero scenario: 103.1 MtAnnounced supply projects: 88.8 Mt2036 (projection)Baseline scenario: 95.9 MtNet Zero scenario: 106.5 MtAnnounced supply projects: 90.4 Mt2037 (projection)Baseline scenario: 98.3 MtNet Zero scenario: 110.0 MtAnnounced supply projects: 92.1 Mt2038 (projection)Baseline scenario: 100.7 MtNet Zero scenario: 113.7 MtAnnounced supply projects: 93.7 Mt2039 (projection)Baseline scenario: 103.1 MtNet Zero scenario: 117.5 MtAnnounced supply projects: 95.5 Mt2040 (projection)Baseline scenario: 105.6 MtNet Zero scenario: 121.4 MtAnnounced supply projects: 97.2 Mt

Hover over the chart to read values for each year.

View the data
YearObserved consumptionBaseline scenarioNet Zero scenarioAnnounced supply projects
200123.6
200225.5
200327.6
200430.0
200531.6
200633.9
200737.4
200837.0
200934.8
201040.4
201144.9
201249.3
201346.5
201454.0
201557.4
201659.0
201763.2
201866.0
201963.2
202064.8
202168.5
202268.1
202369.3
202472.072.072.072.8
202573.774.474.1
202675.576.875.4
202777.379.476.8
202879.282.078.2
202981.184.779.6
203083.187.581.1
203185.190.582.6
203287.293.584.1
203389.396.685.6
203491.599.887.2
203593.7103.188.8
203695.9106.590.4
203798.3110.092.1
2038100.7113.793.7
2039103.1117.595.5
2040105.6121.497.2
Refined copper2035 gap to Net Zero demand: 6.3 Mt (17%)
Observed consumptionObserved productionBaseline scenario (demand)Net Zero scenario (demand)Announced supply projects
Projections01020304050200120052010201520202025203020352040Mt2001Observed consumption: 13.3 Mt2002Observed consumption: 14.8 Mt2003Observed consumption: 15.1 MtObserved production: 15.2 Mt2004Observed consumption: 16.4 MtObserved production: 14.5 Mt2005Observed consumption: 16.6 MtObserved production: 16.5 Mt2006Observed consumption: 16.9 MtObserved production: 17.3 Mt2007Observed consumption: 18.0 MtObserved production: 18.1 Mt2008Observed consumption: 18.1 MtObserved production: 18.4 Mt2009Observed consumption: 18.1 MtObserved production: 18.4 Mt2010Observed consumption: 19.3 MtObserved production: 19.1 Mt2011Observed consumption: 19.6 MtObserved production: 19.6 Mt2012Observed consumption: 20.3 MtObserved production: 20.1 Mt2013Observed consumption: 21.1 MtObserved production: 21.2 Mt2014Observed consumption: 22.8 MtObserved production: 22.6 Mt2015Observed consumption: 22.8 MtObserved production: 22.8 Mt2016Observed consumption: 23.2 MtObserved production: 23.4 Mt2017Observed consumption: 23.2 MtObserved production: 23.5 Mt2018Observed consumption: 23.8 MtObserved production: 23.8 Mt2019Observed consumption: 23.9 MtObserved production: 24.0 Mt2020Observed consumption: 24.8 MtObserved production: 24.4 Mt2021Observed consumption: 24.8 MtObserved production: 24.8 Mt2022Observed consumption: 25.9 MtObserved production: 25.7 Mt2023Observed consumption: 26.6 MtObserved production: 27.2 Mt2024Observed consumption: 26.9 MtObserved production: 27.6 MtBaseline scenario: 26.9 MtNet Zero scenario: 26.9 MtAnnounced supply projects: 26.9 Mt2025 (projection)Baseline scenario: 27.5 MtNet Zero scenario: 28.4 MtAnnounced supply projects: 27.8 Mt2026 (projection)Baseline scenario: 28.0 MtNet Zero scenario: 29.8 MtAnnounced supply projects: 28.9 Mt2027 (projection)Baseline scenario: 28.6 MtNet Zero scenario: 31.3 MtAnnounced supply projects: 30.0 Mt2028 (projection)Baseline scenario: 29.1 MtNet Zero scenario: 32.8 MtAnnounced supply projects: 31.4 Mt2029 (projection)Baseline scenario: 29.7 MtNet Zero scenario: 34.2 MtAnnounced supply projects: 32.5 Mt2030 (projection)Baseline scenario: 30.3 MtNet Zero scenario: 35.0 MtAnnounced supply projects: 33.2 Mt2031 (projection)Baseline scenario: 30.9 MtNet Zero scenario: 35.8 MtAnnounced supply projects: 33.4 Mt2032 (projection)Baseline scenario: 31.5 MtNet Zero scenario: 36.6 MtAnnounced supply projects: 33.1 Mt2033 (projection)Baseline scenario: 32.1 MtNet Zero scenario: 37.4 MtAnnounced supply projects: 32.6 Mt2034 (projection)Baseline scenario: 32.7 MtNet Zero scenario: 38.1 MtAnnounced supply projects: 32.3 Mt2035 (projection)Baseline scenario: 33.4 MtNet Zero scenario: 38.3 MtAnnounced supply projects: 32.0 Mt2036 (projection)Baseline scenario: 34.0 MtNet Zero scenario: 38.5 MtAnnounced supply projects: 31.7 Mt2037 (projection)Baseline scenario: 34.7 MtNet Zero scenario: 38.7 MtAnnounced supply projects: 31.6 Mt2038 (projection)Baseline scenario: 35.4 MtNet Zero scenario: 38.9 MtAnnounced supply projects: 31.4 Mt2039 (projection)Baseline scenario: 36.1 MtNet Zero scenario: 39.4 MtAnnounced supply projects: 31.3 Mt2040 (projection)Baseline scenario: 36.8 MtNet Zero scenario: 40.0 MtAnnounced supply projects: 31.1 Mt

Hover over the chart to read values for each year.

View the data
YearObserved consumptionObserved productionBaseline scenarioNet Zero scenarioAnnounced supply projects
200113.3
200214.8
200315.115.2
200416.414.5
200516.616.5
200616.917.3
200718.018.1
200818.118.4
200918.118.4
201019.319.1
201119.619.6
201220.320.1
201321.121.2
201422.822.6
201522.822.8
201623.223.4
201723.223.5
201823.823.8
201923.924.0
202024.824.4
202124.824.8
202225.925.7
202326.627.2
202426.927.626.926.926.9
202527.528.427.8
202628.029.828.9
202728.631.330.0
202829.132.831.4
202929.734.232.5
203030.335.033.2
203130.935.833.4
203231.536.633.1
203332.137.432.6
203432.738.132.3
203533.438.332.0
203634.038.531.7
203734.738.731.6
203835.438.931.4
203936.139.431.3
204036.840.031.1
Refined nickel2035 gap to Net Zero demand: 2.29 Mt (34%)
Observed consumptionObserved productionBaseline scenario (demand)Net Zero scenario (demand)Announced supply projects
Projections02.557.51012.5200120052010201520202025203020352040Mt2001Observed consumption: 1.04 MtObserved production: 1.19 Mt2002Observed consumption: 1.17 MtObserved production: 1.21 Mt2003Observed consumption: 1.25 MtObserved production: 1.22 Mt2004Observed consumption: 1.24 MtObserved production: 1.25 Mt2005Observed consumption: 1.32 MtObserved production: 1.27 Mt2006Observed consumption: 1.37 MtObserved production: 1.35 Mt2007Observed consumption: 1.35 MtObserved production: 1.41 Mt2008Observed consumption: 1.34 MtObserved production: 1.37 Mt2009Observed consumption: 1.31 MtObserved production: 1.32 Mt2010Observed consumption: 1.43 MtObserved production: 1.44 Mt2011Observed consumption: 1.65 MtObserved production: 1.60 Mt2012Observed consumption: 1.73 MtObserved production: 1.76 Mt2013Observed consumption: 1.80 MtObserved production: 1.96 Mt2014Observed consumption: 1.58 MtObserved production: 1.99 Mt2015Observed consumption: 1.73 MtObserved production: 1.98 Mt2016Observed consumption: 1.86 MtObserved production: 1.99 Mt2017Observed consumption: 2.09 MtObserved production: 2.07 Mt2018Observed consumption: 2.34 MtObserved production: 2.18 Mt2019Observed consumption: 2.43 MtObserved production: 2.37 Mt2020Observed consumption: 2.44 MtObserved production: 2.49 Mt2021Observed consumption: 2.96 MtObserved production: 2.61 Mt2022Observed consumption: 3.01 MtObserved production: 3.06 Mt2023Observed consumption: 3.20 MtObserved production: 3.37 Mt2024Observed consumption: 3.45 MtObserved production: 3.53 MtBaseline scenario: 3.45 MtNet Zero scenario: 3.45 MtAnnounced supply projects: 3.45 Mt2025 (projection)Baseline scenario: 3.70 MtNet Zero scenario: 3.77 MtAnnounced supply projects: 3.54 Mt2026 (projection)Baseline scenario: 3.97 MtNet Zero scenario: 4.09 MtAnnounced supply projects: 3.73 Mt2027 (projection)Baseline scenario: 4.25 MtNet Zero scenario: 4.41 MtAnnounced supply projects: 3.93 Mt2028 (projection)Baseline scenario: 4.56 MtNet Zero scenario: 4.72 MtAnnounced supply projects: 4.12 Mt2029 (projection)Baseline scenario: 4.89 MtNet Zero scenario: 5.04 MtAnnounced supply projects: 4.31 Mt2030 (projection)Baseline scenario: 5.24 MtNet Zero scenario: 5.36 MtAnnounced supply projects: 4.50 Mt2031 (projection)Baseline scenario: 5.62 MtNet Zero scenario: 5.63 MtAnnounced supply projects: 4.49 Mt2032 (projection)Baseline scenario: 6.02 MtNet Zero scenario: 5.90 MtAnnounced supply projects: 4.47 Mt2033 (projection)Baseline scenario: 6.45 MtNet Zero scenario: 6.17 MtAnnounced supply projects: 4.46 Mt2034 (projection)Baseline scenario: 6.92 MtNet Zero scenario: 6.44 MtAnnounced supply projects: 4.44 Mt2035 (projection)Baseline scenario: 7.42 MtNet Zero scenario: 6.71 MtAnnounced supply projects: 4.43 Mt2036 (projection)Baseline scenario: 7.95 MtNet Zero scenario: 6.71 MtAnnounced supply projects: 4.43 Mt2037 (projection)Baseline scenario: 8.52 MtNet Zero scenario: 6.79 MtAnnounced supply projects: 4.43 Mt2038 (projection)Baseline scenario: 9.13 MtNet Zero scenario: 6.86 MtAnnounced supply projects: 4.43 Mt2039 (projection)Baseline scenario: 9.79 MtNet Zero scenario: 6.93 MtAnnounced supply projects: 4.43 Mt2040 (projection)Baseline scenario: 10.50 MtNet Zero scenario: 7.08 MtAnnounced supply projects: 4.43 Mt

Hover over the chart to read values for each year.

View the data
YearObserved consumptionObserved productionBaseline scenarioNet Zero scenarioAnnounced supply projects
20011.041.19
20021.171.21
20031.251.22
20041.241.25
20051.321.27
20061.371.35
20071.351.41
20081.341.37
20091.311.32
20101.431.44
20111.651.60
20121.731.76
20131.801.96
20141.581.99
20151.731.98
20161.861.99
20172.092.07
20182.342.18
20192.432.37
20202.442.49
20212.962.61
20223.013.06
20233.203.37
20243.453.533.453.453.45
20253.703.773.54
20263.974.093.73
20274.254.413.93
20284.564.724.12
20294.895.044.31
20305.245.364.50
20315.625.634.49
20326.025.904.47
20336.456.174.46
20346.926.444.44
20357.426.714.43
20367.956.714.43
20378.526.794.43
20389.136.864.43
20399.796.934.43
204010.507.084.43

Gap = Net Zero scenario demand minus announced supply projects in 2035. Source: Coface, Back to the Future (Cycle), using data from USGS, WorldSteel, ICSG, IAI, INSG, IZA and the IEA.

Beijing’s hold on refining

China holds around 70% of refining capacity for 19 of 20 key minerals, and produces more than half of the world’s steel, aluminium and refined copper. But mining is one matter; refining another. A vehicle manufacturer can diversify its ore sources and yet still depend on one country’s refineries for the metal that reaches the plant gate. Sourcing strategies that stop at the first tier of the supplier map will miss this exposure entirely.

Head-and-shoulders studio portrait of a young man with dark hair and a beard against a grey background.
Marcos Carias, North America Economist at Coface

Mines move slower than model cycles

Fewer than 1% of exploration projects become working mines, and development timelines of 15 to 20 years limit how quickly output can respond to higher prices. A vehicle platform is planned, tooled and retired in a fraction of that time. The usual economic reflex, in which higher prices summon new supply, works on a clock that carmakers cannot wait out.

The copper stuck in America

Marcos Carias, North America Economist at Coface, says tariff uncertainty has left an unusually large amount of copper stuck in the US. Once there is clarity, he expects some of it to flow back out, which could actually push prices down in the near term. Meanwhile, companies are holding off on new US smelters and refineries until they know what the tariffs will look like.

So relief may arrive just as the long-term squeeze tightens, and the first may be mistaken for the end of the second. Carias is blunt about the implication when he says, “for manufacturers in the US, Canada and Mexico, that means planning for higher metal costs over the long term instead of waiting for a trade deal to bring prices back down.”

The AMS Survey: Steel buyers are already hedging

Daniel Harrison speaks at a podium with microphones beside a laptop on stage.
Daniel Harrison, Senior Automotive Analyst at Ultima Media

Steel sits outside Coface’s headline warning on copper and nickel, yet it is the metal carmakers know best, and how they buy it hints at how they may respond to the squeeze elsewhere. A survey by AMS, carried out with steelmaker SSAB, gathered 307 responses from OEMs, Tier suppliers and engineering firms in May and June 2026, with a margin of error of 5.56% at a 95% confidence level.

And price, as opposed to other variables, still rules the purchasing desk. Cost effectiveness was rated important by 86% of respondents choosing steel for automotive applications, ahead of strength and durability and weldability (both 84%) and manufacturability (83%). Cost was also the leading barrier to low-carbon steel, cited by 41%, although that was down sharply from 74% in the 2024 edition.

The more telling shift, however, lies in recycled content. Some 72% of respondents to the AMS survey now have a recycled steel target, up from 46% two years earlier, and 82% have an agreement with either a recycling company (39%) or a steel supplier (37%).

Meanwhile, one in five (20%) has gone further, with a closed loop arrangement with a steel supplier. The survey framed such deals as a sustainability measure - but they also work as a supply measure.

A plant that controls its scrap returns depends less on the primary market, which is precisely the exposure Coface describes. If that mechanism spreads from steel to aluminium and copper, the next round of supplier contracts may look quite different.

Costing for a different decade

For engineering and purchasing teams, the question shifts from when prices will fall to how a design survives when they do not. Can a harness be redesigned to use less copper? Which castings could take a different alloy? Where does recycled content, secured early, become a hedge rather than a sustainability line?

Plants that answer these questions while metal is merely expensive will be better placed than those that wait until it is scarce.