US plant

BMW starts Gen6 battery production at Woodruff

Published Modified
3 min
An employee at the Woodruff plant.

BMW has opened its new high-voltage battery assembly plant in South Carolina, marking a key milestone in its US electrification strategy. The facility combines 250 robots, AI-driven quality control and virtual reality training to supply the nearby Spartanburg vehicle plant.

BMW has officially opened Plant Woodruff in South Carolina and commenced series production of its sixth-generation (Gen6) high-voltage batteries. Located just 15 miles from Plant Spartanburg, the facility will supply batteries for the fully electric BMW iX5 and subsequent electric models manufactured in the US.

The opening represents a major step towards BMW's first series production of fully electric vehicles in the Americas. The carmaker plans to manufacture at least six fully electric models at Spartanburg by 2030, beginning with the iX5.

The start of operations also completes a key phase of BMW's $1.7 billion transformation of its Spartanburg manufacturing operations, which includes upgrades to vehicle assembly infrastructure and the construction of the new battery facility.

AI and automation support zero-defect battery production

More than 300 employees and 250 robots operate at Woodruff, where BMW has implemented extensive inline quality monitoring and real-time production data analysis. In-house-developed AI assistants and agents evaluate manufacturing data to identify potential defects and improve overall equipment effectiveness (OEE). The plant produces Gen6 battery packs using cylindrical cells integrated directly into the battery housing through a cell-to-pack architecture, eliminating intermediate modules.

Following incoming inspection, the cells are assembled into clusters and connected to cooling components. Laser cleaning and precision welding are used to join the assemblies, with each weld monitored inline. A foaming process provides mechanical stability and protection before the housing is sealed and the Energy Master central control unit installed.

Every completed battery undergoes a comprehensive end-of-line inspection before shipment to Spartanburg. BMW previously detailed the plant's AI-driven production processes and digital manufacturing systems, which have been developed to support consistent battery quality as production scales up.

Virtual factory supports workforce training

Digital manufacturing technologies also played an important role during the facility's development. BMW used digital twins and virtual reality applications to plan production processes and prepare employees before commissioning.

All production employees complete a VR training programme developed specifically for Woodruff. The virtual environment replicates the physical production lines, allowing workers to practise operating procedures and familiarise themselves with equipment before entering the manufacturing environment.

The approach forms part of BMW's broader iFactory manufacturing strategy, which combines digitalisation, flexible production and resource efficiency across its global operations.

Woodruff becomes fourth Gen6 battery production site

Woodruff is the fourth facility in BMW's global Gen6 battery assembly network to enter series production, following Debrecen in Hungary in October 2025 and Irlbach-Straßkirchen in Germany and Shenyang in China in October 2026. A fifth facility in San Luis Potosí, Mexico, is scheduled to follow in 2027.

The network follows BMW's local-for-local strategy, locating battery assembly operations close to vehicle manufacturing plants to reduce transportation requirements and strengthen regional supply chains.

"With the opening of our Woodruff plant, we are expanding our global Gen6 network," said Raymond Wittmann, BMW Board Member responsible for Production. He emphasised the importance of transferring manufacturing expertise between sites to accelerate the industrialisation of the new battery technology.

Three years from groundbreaking to series production

Construction at Woodruff began in September 2023, following the groundbreaking ceremony in June that year. Production equipment installation started in September 2024 while construction was still underway, with the first test and pre-series batteries produced during summer 2025.

The plant has also been designed to reduce the environmental impact of battery manufacturing. According to BMW, the Gen6 cells used in the iX5 have a carbon footprint approximately 28% lower per watt-hour than the previous Gen5 cells used in the BMW iX.

The reduction is attributed partly to higher proportions of secondary materials, including cobalt, lithium and nickel, as well as renewable energy use in electrode material production and cell manufacturing.

Woodruff operates without fossil fuels during normal production, while hydrogen-powered industrial trucks are used for internal material handling.

With series production now underway, the facility establishes the battery manufacturing capacity needed to support BMW's expanding electric vehicle portfolio in Spartanburg and its wider North American production strategy.